IndianaLocalNews

Seitz Park nears completion after multiple delays

(Photo Supplied/City of South Bend and southbendin.gov)
Seitz Park is finally near completion after years behind schedule and millions over budget. South Bend Public Works Director Eric Horvath says it will be worth the wait despite the delays.
Renovations took over four years due to two big projects: Notre Dame’s installation of hydroelectric turbines under the park and then the park’s reconstruction.
Construction couldn’t start until the turbines were in place, and COVID added another year to the delay.

Related posts

2026 Michigan Primary Election Results

Jon Zimney

August Food Bank of Northern Indiana Mobile Food Distributions

95.3 MNC

Suspect arraigned on multiple felony charges after armed disturbance in Lincoln Township

Jon Zimney

Leave a Comment