The second phase of a bridge replacement project on the U.S. 20/31 by pass is starting in August.

As work zones are set up, traffic routes will change.

The westbound U.S. 20 bridge will be closed and the new eastbound bridge is going to be used for two-way traffic.

From August 8-20, overnight road closures will be happening for the bridge demolition, on U.S 31, under the U.S 20 bridge.

Closures will happen from 9 p.m. to 6 a.m. those days.

Traffic will be detoured off of U.S 31.

Work is set to happen through early December.